Important: “Weekend Days” are considered Saturday and Sunday in ActiLife5 while “Weekdays”
are considered Monday thru Friday.
Dataset Qualifier Example:
- Minimum number of days to wear: 6
- Minimum number of weekdays to wear: 3
- Minimum number of weekend days to wear: 3
- Note that “weekend days” refer to the total weekend days available in the dataset; not the weekend days per
week. In this example, the dataset is 14 days long and covers two weekends or four possible weekend days.
- Stage 2 filter settings reveal that a particular dataset that starts on Monday, January 4 contains 14 days’ worth
of consecutive data but results in only 6 days’ worth of “valid” data
- The “valid” days fall on
- Wednesday, Jan 6
- Thursday, Jan 7
- Friday, Jan 8
- Saturday, Jan 9
- Monday, Jan 11
- Thursday, Jan 14
- This dataset would be considered INVALID because it does not meet the minimum weekend day’s requirement.
Although the “Minimum number of days to wear” criteria of six (6) days are met, only Saturday, January 9
qualifies as a valid weekend day.
Running Wear Time Validation
Figure 43Get Results Option Runs Wear Time Validation Filtering